start [2012/02/20 09:12]
jacobs
start [2012/03/23 08:44]
jacobs
Line 6: Line 6:
  
 ====== OPERATION PROCEDURES ====== ====== OPERATION PROCEDURES ======
 +
  
 ===== Shift Change of Operator ===== ===== Shift Change of Operator =====
  
  * [[playground:​shift|Shift Change Procedure]]  * [[playground:​shift|Shift Change Procedure]]
 +
 +
 +===== Manning the Control Console =====
 +
 +  * [[playground:​console|Console Policy]]
 +
 +
  
  
Line 18: Line 26:
 ===== General Safe Operating Procedures ===== ===== General Safe Operating Procedures =====
  
-  * See Sections III, IV, V, and VI of the Radiation Safety Handbook+  * [[http://​www.ohio.edu/​riskandsafety/​radiationsafety/​rad_saf_handbook.htm#​Htoc|See Sections III, IV, V, VI, and IX of the Radiation Safety Handbook]]
  
  
Line 35: Line 43:
  * [[playground:​trip|Over Voltage Trip]]  * [[playground:​trip|Over Voltage Trip]]
   * [[playground:​spark|Spark Instructions]]   * [[playground:​spark|Spark Instructions]]
 +
 +
 +
 +
 +
 +
 +
 +
 +
 +
 +
 +
  
  
Line 42: Line 62:
 ===== Beam Operations ===== ===== Beam Operations =====
  
 +  * {{buncher_tables.pdf|Buncher/​Extractor Tables}}
  * [[playground:​pulsing|Pulsing and Bunching]]  * [[playground:​pulsing|Pulsing and Bunching]]
 +  * [[playground:​quadControls|Computer Control of Quadrupoles]]
   * [[playground:​changeleg|Changing Legs]]   * [[playground:​changeleg|Changing Legs]]
   * [[playground:​nmr|NMR Setup]]   * [[playground:​nmr|NMR Setup]]
 +  * [[playground:​integrator|Beam Current Integrator]]
 +
 +  * Beam Energy: ​ E = Terminal(charge state + 1) + injection energy
 +
 +  * Slits and Energy Resolution: ​ dE/E = 2(dR/​R) ​   ! R = 28", dR is aperture size (each slit is 1/2 dR)
 +
  
 ===== Facility Shutdown ===== ===== Facility Shutdown =====
Line 71: Line 99:
         * [[playground:​power|Short Interuption (<1 min)]]         * [[playground:​power|Short Interuption (<1 min)]]
   * [[playground:​powerout|Long Interuption ( >1 min)]]   * [[playground:​powerout|Long Interuption ( >1 min)]]
 +
  
 ===== Chemical & Radiation Emergencies ===== ===== Chemical & Radiation Emergencies =====
  
-  * See Section VIII of the Radiation Safety Handbook+  * [[http://​www.ohio.edu/​riskandsafety/​radiationsafety/​rad_saf_handbook.htm#​Htoc|See Section VIII of the Radiation Safety Handbook]]
  
 ===== Tritium Emergency ===== ===== Tritium Emergency =====
Line 83: Line 112:
  
 ====== TESTING, CALIBRATION,​ & SHUTDOWN ====== ====== TESTING, CALIBRATION,​ & SHUTDOWN ======
 +
  
  
Line 89: Line 119:
   * [[playground:​interlock|Policy and Rules]]   * [[playground:​interlock|Policy and Rules]]
  
 +
 +
 +===== Testing and Shutdown Logs =====
 +
 +  * {{shutdown_test_log.pdf|Shutdown Test Log (blank form)}}
 +  * {{safety_warning_test_log.pdf|Safety & Warning Device Test Log (blank form)}}
 +  * {{accidental_shutdown_log.pdf|Accidental Shutdown Log (blank form)}}
  
  
Line 108: Line 145:
  
   * {{personnel_classifications.pdf|Accelerator Personnel Classifications}}   * {{personnel_classifications.pdf|Accelerator Personnel Classifications}}
 +
  
  
Line 114: Line 152:
   * {{control_room_books.pdf|Content and Inter-relation}}   * {{control_room_books.pdf|Content and Inter-relation}}
  
 +
 +===== Key Holder Training Flow =====
 +
 +  * {{key_holder_training_flow.pdf|Checklist}}
  
  
 ===== Operator 1 Training Flow ===== ===== Operator 1 Training Flow =====
  
-  * {{op1temp.pdf|Checklist}}+  * {{operator_1_training_flow.pdf|Checklist}} 
 + 
 + 
 + 
 +===== Operator 2 Training Flow ===== 
 + 
 +  * {{operator_2_training_flow.pdf|Checklist}} 
 + 
 + 
 + 
 + 
 + 
 + 
 + 
 +====== Resource Materials ====== 
 + 
 +===== Lab Layout ===== 
 + 
 +  *[[Lab Layout]] 
 + 
 +===== OUAL Tandem Accelerator ===== 
 + 
 +  * [[playground:​structure|Tank,​ Tubes, & Column]] 
 +  * [[playground:​stripping|Terminal Stripping]] 
 +  * [[playground:​pelletron|Pelletron Theory, OUAL Installation]] 
 +  * [[playground:​TPS control|Terminal Potential Stabilizer Function and Components]] 
 +  * [[playground:​control modules|Panel Fronts and Labeling]] 
 + 
 + 
 +===== Electrostatic Components ===== 
 + 
 +  * [[playground:​Einzel|Einzel Lenses]] 
 +  * [[playground:​grid|Gridded Lenses]] 
 +  * [[playground:​steerers|Electrostatic Steerers]] 
 + 
 + 
 +===== Magnets ===== 
 + 
 +4 Bending Magnets: ​ Inflection, Analyzer, Switcher, and Swinger 
 + 
 +[[playground:​quads|Quadrupoles]] 
 + 
 + 
 + 
 + 
 + 
 +===== Beam Measurement ===== 
 + 
 + 
 +  * [[Faraday Cups]] 
 +  * [[Current Meters]] 
 +  * [[Beam Profile Monitors]] 
 +  * [[Beam Pick Off]] 
 +  * [[playground:​integrator|Beam Current Integrator (from the Beam Operations Section of the Operating Proceedures Book)]] 
 + 
  
  
  
start.txt · Last modified: 2023/09/08 13:06 by carter