playground:sputter [2010/07/30 10:00]
132.235.40.102
playground:sputter [2010/07/30 10:03]
132.235.40.102
Line 38: Line 38:
   - The source gate valve should be closed for this operation.   - The source gate valve should be closed for this operation.
   - Wait for normal vacuum. ​ Normal is when the needle is in the blue mark on the gauge above the TV in the control room.   - Wait for normal vacuum. ​ Normal is when the needle is in the blue mark on the gauge above the TV in the control room.
-  - Set ionizer to 10A.� This will lead to a rise in the vacuum pressure.+  - Set ionizer to 10A. This will lead to a rise in the vacuum pressure.
   - Wait for vacuum to fall back to the blue mark on the gauge   - Wait for vacuum to fall back to the blue mark on the gauge
-  - Raise the ionizer by an additional� 2-3 A and wait for the vacuum to fall back into the blue range. +  - Raise the ionizer by an additional 2-3 A and wait for the vacuum to fall back into the blue range. 
-  - Repeat this process until the ionizer is at 21 A and the vacuum is in the blue range.+  - Repeat this process until the ionizer is at 21 A and the vacuum is in the blue range, may take 8 hours.
   - Open the source gate valve and carry out the Startup and Normal Operation.   - Open the source gate valve and carry out the Startup and Normal Operation.
  
Line 67: Line 67:
 Telephone: (740)593-0933\\ Telephone: (740)593-0933\\
 E-Mail: massey@ohio.edu\\ E-Mail: massey@ohio.edu\\
-Last modified on 12/06/2006\\+Last modified on 7/30/2010 DKJ\\
  
  
playground/sputter.txt · Last modified: 2023/08/22 07:50 by carter