| ====== Accelerator Start-up ====== | ====== Accelerator Start-up ====== | ||
| + | |||
| + | === ==== ** Clear all Areas ** ==== === | ||
| + | |||
| 1. **Verify Initial Machine Voltage setup:** | 1. **Verify Initial Machine Voltage setup:** | ||
| Line 24: | Line 27: | ||
| * POWER: | * POWER: | ||
| * CABLE: | * CABLE: | ||
| - | |||
| Line 37: | Line 39: | ||
| **2. Corona Probe Adjustment** | **2. Corona Probe Adjustment** | ||
| - | After reaching the approximate desired terminal voltage with no corona current present, begin moving the corona points in. Maintain the desired approximate terminal voltage by increasing the UPCHARGE and iteratively move the corona points in while restoring the terminal voltage with the UPCHARGE. | + | After reaching the approximate desired terminal voltage with no corona current present, begin moving the corona points in (set corona current/ |
| a. Move the CORONA PROBE POSITION “IN” to make the GRID VOLTAGE more negative. | a. Move the CORONA PROBE POSITION “IN” to make the GRID VOLTAGE more negative. | ||
| Line 53: | Line 55: | ||
| b. Slowly raise the CONTROL GAIN to 2-3 for low current beams, around 5 for high current beams. | b. Slowly raise the CONTROL GAIN to 2-3 for low current beams, around 5 for high current beams. | ||
| - | c. Make fine adjustments to the TERMINAL VOLTAGE Dial to reach exactly the desired GVM value. | + | c. Make fine adjustments to the TERMINAL VOLTAGE Dial to reach exactly the desired GVM value. Very fine adjustments to the terminal voltage can be made using the FINE control located coaxial to the BIAS CURRENT control with a full range of 1.5 KV. |
| d. Switch OVERVOLTAGE PROTECTION to ENABLE. | d. Switch OVERVOLTAGE PROTECTION to ENABLE. | ||
| + | |||
| + | e. Do accelerator header and collect the NMR frequency and analyzer magnet current values. | ||
| **4. Beam Transport** | **4. Beam Transport** | ||
| - | a. Use the magnet predictor tool and set Quad 1 to the predicted value. | + | a. Use the magnet predictor tool and set Quad 1 to the predicted value. Do not make large abrupt changes to the Quad 1 current. |
| b. Tune beam and send it around the properly configured Analyzing Magnet. | b. Tune beam and send it around the properly configured Analyzing Magnet. | ||
| Line 68: | Line 72: | ||
| e. When in AUTO control the machine will go back to GVM control anytime the beam is interrupted. | e. When in AUTO control the machine will go back to GVM control anytime the beam is interrupted. | ||
| + | |||
| + | **5. Dipole Magnet Setup Instructions** | ||
| + | |||
| + | a. Confirm that the Heinzinger power supplies are powered ON in the Small Target Room with the following LED's illuminated: | ||
| + | |||
| + | b. If not already visible on the control room computer screen, start the appropriate software GUI's using the " | ||
| + | |||
| + | c. In the " | ||
| + | |||
| + | d. Run the slider to the desired current. | ||
| + | |||